Backfilling of Wolfswinkel outer harbor
construction log

04.04.2025

Backfilling of Wolfswinkel outer harbor

Wolfswinkel – backfilling of upper outer harbor

Now that the construction road in Wolfswinkel has been completed and a culvert for a rivulet has also been upgraded so that it can be used by heavy loads, the upper outer harbor is currently being backfilled. Approximately 2200 m³ of soil is required to create a sufficiently large movement area for the upcoming work.